    Christian Hermes
    Participant

    Hi,

    i have a Problem:

    I try to count Days between two Dates. I Use (like described here):
    [End Date] – [Start Date] /60 /60 /24

    The Result looks like: 1.409.134.579
    (for 28.08.2014 – 27.08.2014)

    Where is my fault ?

    Thanks Chris

    Attachments:
    You must be logged in to view attached files.
    August 27, 2014 at 11:24 AM #10701

    Brendan
    Keymaster

    Hi Christian,

    Get rid of the [ ] square brackets from your formula.

    Thanks!

    Brendan

    August 28, 2014 at 2:45 AM #10703

    Christian Hermes
    Participant

    Thanks Brendan, that works for me ….